ERP Implementation in 90 Days
What each phase looks like, who owns it, and the decisions that decide whether you go live on time.
Ninety days is a real date for a single-site discrete manufacturer that pilots one product line before it widens, moves open orders and current master data only, and has one person who can give the project a day a week without a customer losing a shipment. It is not a real date if you intend to carry ten years of closed job history across, or go live in every department at once, or hold the scope open while the shop keeps asking for one more thing. The timeline is a consequence of scope, not a target you hit by working harder.
Decide what moves and what stays behind
Scope is the only real lever you have on the date. You cannot add people fast enough to buy back a week, and you cannot shorten the pilot without losing the thing the pilot is for. What you can do is decide, in the first fortnight, what crosses into the new system and what does not.
Four things move. Open sales and purchase orders, because work in flight has to be visible where people are looking. Items you actually buy, make or sell today. The bills of material and routings for those items, at the revision currently in production. On-hand balances as of the cutover count, not as of the last time anyone trusted the figures. That list is short on purpose.
Most history stays behind. Closed job costs, quotes that never became orders, superseded revisions, years of goods receipts — all of it stays readable in the old system and none of it comes across. You will be asked for last year's actual cost on a repeat part, and the answer will be that you look it up where it was recorded. That is a worse answer than having everything in one place, and it is the trade you make for a date.
Every "while we are at it" is a week. Barcode labels, a numbering scheme beyond what migration forces, a quality module nobody has written procedures for, custom reports that match the old ones page for page. Each is defensible alone and fatal in aggregate.
The artefact is a one-page scope, signed by whoever controls the budget, with an explicit not-in-scope list on the same page. The not-in-scope list is the half that gets used.
A one-page scope exists, signed by the budget holder, with open orders, current items, current bills and routings and on-hand balances in scope, and everything else listed as explicitly out. Nothing else starts until that page is signed.
Clean the item master before you migrate
This is the phase that overruns, and nobody finds it interesting. Export the item master to a spreadsheet and read every row. Expect duplicate part numbers that differ by a space or a trailing letter, the same raw material stocked in both feet and inches, descriptions that encode the revision so a revision bump created a second item, units of measure that were whatever the first purchase order happened to say, and a long tail of items nobody has bought or sold in six years.
Do the work in the export, where sort, filter and find-and-replace still work and where a mistake costs an undo rather than a correction across linked records. Once an item is in the new system with transactions against it, merging two duplicates stops being a cell edit and becomes a project.
Decide the numbering convention now and write it down in a sentence anyone can apply: significant or non-significant, how a revision is expressed, whether purchased and manufactured parts differ. Renumbering later touches every bill of material, every routing and every open order that references the part, which is why a deferred numbering decision never gets made.
Flag obsolete items rather than deleting them, and import the flag. You want them out of the pick list and still searchable when a customer orders a spare for something you stopped building.
Three columns decide more than the rest: part number, unit of measure, and make or buy. Bills of material, purchasing, stock and costing all read from them.
The artefact is an approved item file that imports into a test environment with no errors, plus a one-paragraph numbering standard. Run the import twice. The second run is the one that tells you the file is clean.
The item file imports into a test environment twice with no errors: duplicates merged, units of measure consistent, obsolete items flagged rather than deleted, and the numbering convention written down somewhere the next person will find it.
Pilot one product line end to end
Pick one product line and run a real job through it, quote to invoice. Representative, not your worst: a bill of material with a level or two, a routing with more than one operation, at least one purchased component and a real inspection step. Your most complex assembly teaches you the most and takes too long to teach it.
Walk the whole chain in the new system with the people who will do it in production. Quote, sales order, bill of material, routing, purchase order, receipt, work order, build, inspection, shipment, invoice. The person who will enter receipts enters the receipt. You are not demonstrating software; you are finding out whether the process you described on the scope page actually exists.
It will not, entirely. The pilot is where you meet the routing nobody documented, the operation one person does by eye, the approval that is really a conversation at the bench, and the packing a customer asked for years ago that lives in one head. Each of those is a decision about how the shop will work rather than a configuration question, and the person who owns the line has to make it.
Fix the process before you widen. A workaround that one line tolerates becomes a habit across six, and habits are what you spend the following year unwinding.
The artefact is a completed job in the new system with its paperwork attached, and a gap list where every item is closed, scheduled, or deferred with a name against it. Widen with the gap list still open and you inherit the same gaps six more times.
One real job has travelled quote to invoice in the new system, entered by the people who will do that work daily, and every gap it exposed is closed, scheduled, or deferred with a name against it.
Cut over and keep the old system readable
Pick the cutover date early and pick it near a natural low point: a shutdown week, the end of a thin month, the days after a large shipment clears. Avoid month-end close and your biggest customer's delivery window.
The week before is a count and a freeze. Stop raising new orders in the old system two or three days out, count stock, enter the counted balances as opening quantities, and key the orders that moved during the freeze by hand. A small amount of manual entry inside a controlled window beats a clever reconciliation afterwards.
Then set the old system to read-only and leave it there. Do not delete it, do not cancel access the week you go live, and do not let anyone write to it again. Read-only is what makes the history question answerable without reopening the scope argument. Keep it reachable for as long as your retention policy requires, and past your first audit after go-live.
Plan for a bad first week and staff it. Put whoever knows the new system on the floor rather than at a desk, standing at receiving and at shipping, where the transactions people get wrong actually happen. Expect the first shipment to take three times as long, and expect a nightly list of things that look wrong, most of which are entry errors and a few of which are real.
Do not run both systems in parallel as a safety net. Parallel running is how a shop ends up maintaining two systems, trusting neither, and reconciling them every month instead of working.
The artefact is a cutover checklist with times, names and a rollback point, walked through out loud with the people named on it.
The shop is transacting in the new system, the old one is read-only and still reachable, nothing is being entered twice, and the daily list of things that look wrong is shorter at the end of the first week than at the start.
How long does an ERP implementation actually take?
As long as the scope you signed. One site, one product line piloted, current master data and open orders only, and ninety days is a working plan. Several sites, multi-level configured products, or a decision to bring job history across, and you are looking at a longer project with a different shape. Set the scope, then read the date off it.
Who should own an ERP implementation internally?
One named person who can tell a department no. Not a committee, and not whoever is best with computers, because the hard calls are about how the shop will work rather than about software. Give them a protected day a week, and give each phase a second owner who does the work daily: the item master to the person who knows the parts, the pilot to the line lead.
Should we clean our data before or after migration?
Before, in the spreadsheet export. Sort, filter and find-and-replace work on a file and do not work on a live record with transactions posted against it. Merging two duplicate part numbers before import is a cell edit; merging them afterwards means unpicking bills of material, open orders and stock. Clean the file, import into a test environment, then import again.
Do we need to migrate historical job costs?
Usually not. Closed job costs, old quotes and superseded revisions stay readable in the frozen old system, and the cost of moving them is measured in weeks. What you do need is the current state: items you still transact, the bills and routings in production now, open orders, and counted on-hand balances. Decide this on the scope page, not during the migration.
Why do ERP implementations go over schedule?
Two things cost the date. Scope added after signing, where each request is reasonable on its own and the total is a month. And an item master that is dirtier than the export suggested, so the cleanup that was budgeted at two weeks eats five. Both are visible early if you count the rows and keep the not-in-scope list in front of people.
How to run an evaluation that ends in a decision instead of another round of demos.
Moving Off SpreadsheetsGetting quotes, jobs, and inventory out of workbooks without losing the history in them.
Getting Audit ReadyThe records an auditor asks for, and how to keep them as a by-product of running the job.
See it run against your own parts.
Bring your item master export and the one product line you would pilot first. We will walk these four phases against your own parts and show you where the ninety days goes.