AS9102 First Article Inspection Template
The three AS9102 forms: part number accountability, raw material and special process certification, and characteristic accountability ballooned to the drawing.
Form 1, Part Number Accountability
Part number and name, serial number, FAIR identifier, part and drawing revision levels, manufacturing process reference, purchase order, whether the FAI is detail or assembly, and the baseline part number.
Form 1 Sub-Assembly Index
An indexed list of sub-assembly part numbers with their own FAI report numbers, and whether each is a full or partial FAI with the reason stated.
Form 2, Product Accountability
Every material specification, special process and functional test the drawing calls out, with the specification number, the supplier performing it, whether customer approval was verified, and the certificate of conformance number.
Form 3, Characteristic Accountability
One line per drawing characteristic with its reference location, designator, requirement, measured result, tooling used, any nonconformance number, and an accept or reject verdict picked from a list.
Signature Block
Prepared by, reviewed by, and customer approval lines with dates, on Form 1 where a reviewer looks for them.
The IATF 16949 control plan format: characteristic, specification, measurement method, sample size and frequency, and the reaction plan when it goes out.
PFMEA TemplateProcess failure mode and effects analysis, with severity, occurrence and detection scored into an RPN and the actions that bring it down.
When do I have to produce an FAI?
On a first production run of a new part, and again after a change that could affect the result: a drawing revision, a new tool, a new process, a new supplier, a different location, or a long production gap. Your customer contract defines the triggers, so read it rather than assuming.
What is the difference between a first article and a first piece?
A first piece check is an operator verifying setup before running the batch, and it stays in house. A first article is a formal, documented demonstration that the whole process produces a conforming part, submitted to the customer. They catch different things and one does not substitute for the other.
Do I need all three forms every time?
Form 1 is always required. Form 2 applies where the drawing calls out materials, special processes or functional tests, which in aerospace it almost always does. Form 3 applies wherever there are characteristics to verify, which is every part. In practice all three get completed.
What does characteristic accountability actually mean?
Every characteristic on the drawing is listed and answered, including the ones that pass. Ballooning the drawing and numbering each characteristic is what makes that provable. A Form 3 that lists only the features someone chose to measure is the most common reason an FAI gets rejected.
What happens if a characteristic fails?
Record the measured result as found, enter the nonconformance number in its column, and run the nonconformance through your normal disposition process. An FAI with a documented failure and a disposition is credible. One with no failures and no evidence of measurement is not.
Keep the record, not the spreadsheet.
See how WorkCell produces this report from the work your shop already did.