Capacity Requirements Planning (CRP)
Capacity requirements planning converts planned and released orders into hours of load at each work center, compares that load period by period against the hours actually available, and exposes the overloads a planner must resolve before the material plan becomes a schedule anyone can run.
Capacity requirements planning is the step that asks whether the material plan can actually be built. Material requirements planning produces dated order quantities while assuming hours are free; capacity requirements planning takes those same planned and released orders, walks each one through its routing, and converts it into hours of load on specific work centers in specific periods. The output is a load profile per work center, period by period, laid against the hours that center has.
The conversion is mechanical. Each routing operation carries a setup time and a run time per piece, so an order for 400 pieces at six minutes each plus a two-hour setup is forty-two hours of load on that operation's work center. Available capacity comes from the other side: machines or stations times shifts times hours per shift, derated by a utilization and efficiency factor so the number reflects hours the center will really deliver rather than hours on the clock. Load is placed in the period the operation is scheduled, which means CRP needs the operation dates from the plan, not just the order dates, and queue and move times between operations push load earlier or later than a naive calculation would.
CRP is the detailed sibling of rough-cut capacity planning, which tests the master production schedule against a handful of critical resources before MRP ever runs. Rough-cut is fast and approximate; CRP is slow, part-level, and only possible after the explosion. Neither one schedules. Both are infinite-capacity reports that say where the plan exceeds reality and leave the fix to a human, which is the dividing line between CRP and finite-capacity scheduling, where the tool refuses to overload a center and moves the dates itself.
What practitioners get wrong is the input data. CRP is only as honest as the routings behind it, and routings rot faster than bills of materials because nobody notices a stale cycle time until a load report says a cell has slack it does not have. Standards set years ago on a machine since replaced, setup times that ignore the tooling change, and a utilization factor of one hundred percent all produce a comfortable report and a late shipment. The second error is treating every overload as real, when a week showing one hundred and thirty percent load often resolves itself the moment two orders are pulled forward into the quiet week before it.
In practice a planner runs CRP after each MRP regeneration, scans the load report for the two or three centers over capacity, and clears them by overtime, an outside vendor, a different routing, or a promised date moved with the customer's agreement.
A weldment shop's robotic cell has one robot running two 8-hour shifts, five days a week, which is 80 clock hours. At 85 percent utilization the center offers 68 usable hours in week 20. CRP loads four orders onto it: 22, 18, 26, and 14 hours of setup plus run, totaling 80 hours. The center is 118 percent loaded. The planner pulls the 14-hour order into week 19, which had 30 hours free, and week 20 lands at 97 percent.
What is the difference between CRP and rough-cut capacity planning?
Rough-cut capacity planning tests the master production schedule against a few critical resources before MRP runs, using a rough profile of hours per end item. CRP runs after the explosion and loads every planned and released order through its full routing onto every work center. Rough-cut catches a plan that is hopeless; CRP finds the specific week and machine that breaks.
Do we need CRP if we already run MRP?
You need it whenever the material plan can be built but the hours cannot. If one or two machines gate everything and the supervisor already knows their load, a formal CRP pass adds little. If you have twenty work centers, shared tooling, and a mix that shifts the bottleneck from month to month, the load report is where overloads surface.
How do you calculate available capacity for a work center?
Multiply the number of machines or stations by shifts per day, hours per shift, and working days in the period, then derate for utilization and efficiency. One cell on two 8-hour shifts across five days is 80 clock hours; at 85 percent utilization you plan against 68. Planned maintenance and known downtime come off before the derating, not after.
What are the limits of capacity requirements planning?
CRP reports, it does not solve. It will show a week at one hundred and forty percent load and offer no sequence that fits, because it loads orders into the periods the plan already chose rather than searching for an arrangement that works. It also ignores labor and tooling constraints unless those are modeled as resources of their own.
What data do you need before running CRP?
Routings with current setup and run times for every operation, a work center record for each resource with its shift pattern and derating factors, and operation-level dates from the plan. Missing or stale routing standards are the usual blocker, and the fastest way to find them is to compare a load report against what the floor actually ran last month.