Routing
A routing is the ordered sequence of operations required to make a part, with each operation naming the work center that performs it, the setup time to prepare, the run time per piece, and any tooling, instructions or inspection the step requires.
A routing is the process plan for one item: the ordered list of operations that turn issued material into a finished part. Each operation carries a sequence number, the work center or machine that performs it, a setup time, a run time expressed per piece or per hour, and usually a description, a tool list and a queue or move time between steps. Sequence numbers are normally spaced in tens so an operation can be inserted later without renumbering the whole plan.
The split between setup and run time is the part that matters most and the part most often collapsed. Setup is the fixed time to prepare the work center for the operation regardless of quantity: changing jaws, loading a program, dialing in a first article. Run time is variable and scales with the quantity made. A routing that buries setup inside a single per-piece figure prices a batch of ten as though it were a batch of a thousand, and the resulting schedule shows no benefit to larger lots and no penalty for splitting them.
The work center is the capacity bucket the operation consumes, not necessarily a specific machine. Scheduling loads operations onto work centers and compares that load against each center's available hours, and that is where a routing stops being documentation and becomes a plan. Operations the routing omits still happen on the floor, so a deburr step left out of the plan consumes real hours against no standard and the schedule drifts by exactly that amount on every job.
Standard times are what the schedule is made of. A due date is the sum of setup, run, queue and move times across the routing, multiplied out by quantity and laid against available capacity, so if the standards are wrong the date is wrong in a way no amount of expediting fixes. Standards estimated once and never compared against reported hours decay as tooling, fixtures and operators change, and a routing running twenty percent long will quietly promise dates the shop cannot hold.
A routing sits alongside the bill of materials: the bill says what the part is made of, the routing says how it is made, and a work order combines both for a specific quantity. Shops carry alternate routings for a part that can run on more than one machine, and the alternate needs its own times rather than a copy of the primary. The honest test of a routing is whether reported hours land near the standard without anyone adjusting them afterward.
A gearbox housing routes through four operations. Operation 10, saw cut, 15 minutes setup and 0.5 minutes per piece. Operation 20, rough mill on a vertical machining center, 90 minutes setup and 12 minutes per piece. Operation 30, finish bore, 45 minutes setup and 6 minutes per piece. Operation 40, inspection, no setup and 2 minutes per piece. For 50 pieces that is 2.5 hours of setup and 17.1 hours of run time, so the job needs 19.6 hours of capacity before any queue time.
What is the difference between a routing and a BOM?
A routing describes how a part is made and a bill of materials describes what it is made of. The routing holds operations, work centers, setup and run times, and it feeds scheduling, capacity and labor cost. The bill holds components and quantities, and it feeds purchasing and material cost. Both are required to release a job.
What is the difference between setup time and run time?
Setup time is fixed per operation and does not change with quantity: loading a program, swapping jaws, proving a first article. Run time is per piece and scales with the order quantity. Keeping them separate is what lets a schedule and a quote distinguish a batch of ten from a batch of a thousand on the same machine.
How do I create a routing for a new part?
Walk the part through the shop in the order it will actually be made, number the operations in tens, and assign each one to the work center that will do the work. Record setup and run time separately, add queue and move time between centers, and include the steps people forget, such as deburr, wash and final inspection.
Why do standard times matter for scheduling?
Because the schedule is built from them. Every promised date is the routing's setup, run, queue and move times multiplied by quantity and loaded against capacity, so a routing that is wrong produces dates that are wrong before the job ever starts. Wrong standards also distort quotes and make labor variance impossible to interpret.
How often should routings be reviewed and updated?
Review a routing whenever reported hours diverge from the standard on repeat jobs, and whenever the process itself changes through new tooling, a new fixture or a different machine. A quiet annual comparison of actual against standard across the highest-volume parts catches the slow drift that no single job makes obvious.