Work in Process (WIP)

Work in process is the accumulated cost of material, labor, and applied overhead sitting in jobs that have been started but not finished. It is both a balance sheet inventory account and the running value of everything open on the floor.

WorkCell TeamPublishedUpdated
In Practice

Work in process is the inventory stage between raw material and finished goods, and the general ledger account that holds its value. A steel blank sitting in the rack is raw material. The same blank once it has been milled, deburred, and is waiting for heat treat is work in process, carrying the cost of the steel plus the labor hours spent on it plus the overhead those hours absorbed. When the last operation closes and the part is received to stock, the accumulated cost moves to finished goods.

The account works as a roll-forward. It opens at the prior period's closing balance, is debited by direct material issued to jobs, direct labor reported against operations, and manufacturing overhead applied at the burden rate, and is credited by the cost of goods manufactured, which is the value of everything completed and transferred out. Whatever remains is the closing balance, and it should equal the sum of costs on every job still open. That reconciliation is the real test of a costing system: if the balance in the account does not tie to the jobs on the floor, something was posted to a job that closed, received without cost, or scrapped without a write-off.

Work in process has a physical meaning alongside the financial one, and the two get conflated. The floor talks about WIP as the pile of parts between stations, counted in pieces, and lean practice treats a growing pile as a symptom of a bottleneck and a cause of long lead times. Accounting talks about WIP as dollars. They move together but not proportionally, because a small number of expensive near-finished assemblies can carry more value than a large queue of raw blanks.

What shops get wrong is leaving jobs open. A work order that shipped in March and was never closed keeps a balance in the account, and a hundred of those turn the WIP figure into a graveyard that overstates inventory on the balance sheet and understates cost of goods sold. The mirror error is receiving a job to stock before all its labor and material has posted, which drains cost out of the job and leaves finished goods valued low. Partial completions, rework that reopens a closed order, and overhead applied against hours nobody clocked all show up here, which is why the open-job aging report deserves as much attention as the balance itself.

In a job shop the balance is read two ways each month: as a number the controller ties to the open work orders, and as a list the production manager scans for the job that has been sitting at operation 40 since August.

Ending WIP = Beginning WIP + Direct Materials Issued + Direct Labor + Applied Manufacturing Overhead - Cost of Goods Manufactured (the value transferred out to finished goods).

A machine shop opens March with 84,000 dollars in work in process. During the month it issues 196,000 dollars of material to jobs, reports 71,000 dollars of direct labor, and applies overhead at 24 dollars per machine hour across 2,500 hours, or 60,000 dollars. Jobs completed and received to finished goods carry 341,000 dollars of cost. The closing balance is 84,000 plus 196,000 plus 71,000 plus 60,000 minus 341,000, which is 70,000 dollars spread across nine open work orders.

Frequently Asked Questions

Is work in process the same as work in progress?

They are used interchangeably in most shops and both abbreviate to WIP. Where a distinction is drawn, work in process is the accounting value of unfinished jobs carried as a current asset, while work in progress is the count of those jobs that a shop caps to control lead time. The broader phrase also covers construction and engineering contracts that are not stocked parts.

Do small shops need to track work in process?

If jobs span more than a few days you already have a balance, whether or not anyone reports it. The question is granularity. A shop running two-day jobs can value WIP once a month from open orders and be close enough; a shop with six-week builds and progress billing needs cost on each job as it accumulates.

How is work in process valued?

Sum the direct material issued, the direct labor reported, and the overhead applied to every job still open at the cutoff. Most shops carry it at standard cost and book the variances separately, because actual cost per unit is unknown until the job closes. Partially complete operations are usually valued at the standard through the last operation reported.

Why is high work in process a problem?

It is cash committed to parts that cannot be sold yet, and it lengthens lead time, because a part entering a queue of forty waits behind all forty. It also hides quality problems: a defect made at operation 10 is not found until operation 50, and by then the whole queue between them carries the same fault.

How do you reconcile the WIP account to the floor?

Run the open work order cost report at the same cutoff as the ledger and compare the totals. A gap almost always traces to one of four things: a job received to stock with labor still posting, a closed job that took a late material issue, scrap never written off, or overhead applied at a rate the ledger no longer uses.